All Blog Entries

  1. 8/15/16: some photos

  2. 8/5/16: Odds & Ends

  3. tele is here!

    the tele arrived yesterday. we have it for a month

    here's the plan
    -finish chinking the 15 rows we have left on the outside
    -OSB, tyvek, siding on both the north and the south shed dormer
    -finish framing east and west gable ends (west is almost completed)
    -OSB, tyvek, windows doors, side both gable ends

    we have 5 weeks to do it

    here's to dry days!
    Categories
    Uncategorized
  4. 2016 update

    we're half way through the 2016 building season.

    the grass seed we spread is growing well
    we've been working on finishing chinking; have 23 rows left to chink
    we have 3/4 of the loft floor joists up; we hope to finish next week
    we intend to rent a tele for the month of August to frame side the dormer and gable ends and install all windows and doors on the top floor and also cut out, buck and install all the rest of the exterior windows and doors.

    ...
    Categories
    Uncategorized
  5. garage build summary

    at the request of a fellow LHBA-er, I'm summarizing the garage build

    site clearing


    volunteer log peelers


    garage frost wall


    more garage logs
    ...
    Categories
    Uncategorized
Page 20 of 40 FirstFirst ... 10181920212230 ... LastLast