by
panderson03 on 09-05-2016 at 07:02 PM



will find a pic of north small enough to upload here.
by
panderson03 on 08-27-2016 at 05:57 PM
we finished framing in the west side gable end and started placing OSB, but the month is almost over and we didn't finish our to-do list.
so we're renting the tele for Sept too.
here's what we got done: chinking (chinking is done!!!), north and south dormers got framed, bird blocks in, OSB and tyvek on, windows in.
on the west side gable end, finished framing and started OSB
here's what we still have to do: west side OSB to complete, west side
Read More
by
panderson03 on 08-27-2016 at 05:47 PM
on the cabin north side we got the framing done, bird blocks done, osb done, tyvek done and windows in
by
panderson03 on 08-27-2016 at 05:44 PM
well on the south side of the cabin we got the dormers framed in, bird blocks in, OSB on, tyvek on
by
panderson03 on 07-29-2016 at 09:52 AM
the tele arrived yesterday. we have it for a month
here's the plan
-finish chinking the 15 rows we have left on the outside
-OSB, tyvek, siding on both the north and the south shed dormer
-finish framing east and west gable ends (west is almost completed)
-OSB, tyvek, windows doors, side both gable ends
we have 5 weeks to do it