I might be able to gather half a dozen workers for a solid week of construction, including myself. More could help, but I know there are diminishing returns on head count. Starting on completed piers, how much should I expect to get done in 7 days, weather permitting?
This assumes all tools on site, including a crane or telehandler, and also assumes good, careful planning. This log home will be one story -- can all log stacking be done in a week? The roof deck will be 12" SIP's 8 feet by 24 feet (really!), so I expect those to be quicker than built-up, though I have no experience. The finish roof will be standing seam metal roofing, like LHN, if I recall correctly. Could all the roofing fit in a week, too, realistically?
Things I am not tempted to press for would include windows and doors, or gables, or floors. Or even gutters. ;-)
Peter