wow. REALLY looking forward to this years building season! spring fever and cabin fever converging!
-last year we finished the roof,
-started framing in the gable ends,
-put in black water pipe from the garage to the septic tank,
-bought half the window's we'll need,
-got the log walls cleaned/borated/stained,
-got more than half of the structure chinked.
this year we plan to
-pour basement cement slap
-pour cement footers for porch/deck posts
-finish framing in gable ends
-seed bare dirt between garage and septic tank
-finish chinking
-close up envelope by installing external windows and doors
we'll see how it all plays out!