we're half way through the 2016 building season.

the grass seed we spread is growing well
we've been working on finishing chinking; have 23 rows left to chink
we have 3/4 of the loft floor joists up; we hope to finish next week
we intend to rent a tele for the month of August to frame side the dormer and gable ends and install all windows and doors on the top floor and also cut out, buck and install all the rest of the exterior windows and doors.

before snow fall we plan to put up one side of the warp around deck. if we can complete that and closing up the envelop we'll be delighted