change in plans

Rate this Entry
we have the logs cleaned/borated/stained. got chinking insulation done and 6 of the 8 (4 interior/4 exterior) walls nailed.
but rather than quickly finishing prep and moving on to chinking, we've decided to close up the gable ends (while we still have the rented tele) and chink when we have some spare time (like when its been raining and is too muddy to use the tele).

got the west bottom plates (2 layers of treated 2x10's) down on the west side. have to figure out exactly what our window config will look like and then work on framing in.
we'll be using 2x6's 2' oc.